Rooftop Units Installed | Building Update – Episode #16

custom emergency vehicles

What’s Been Happening

  • Painting at exterior of extension area
  • Interior Glass and Glazing Installation
  • Set rooftop units (RTUs) at both the existing building and new expansion

What’s Coming Up

  • Continued Ceramic and Porcelain Tile Installation
  • Site Fencing and Gates at East Drive
  • Construction of Additional Paint Booths in Expansion Area

Why This Matters

With the units now in place, the building is one step closer to becoming a fully conditioned environmentโ€”critical for the next stages of interior construction. The team is working diligently to seal the building and prep for that first blast of air conditioning. Itโ€™s a significant leap forward that brings us closer to full operational readiness.

Stay tuned for next weekโ€™s update, and thank you for following along on the journey!