What’s Been Happening
- Construction ongoing with Paint Booth #2 & #3
- Arrival of Paint Automation Equipment
- Ceramic and Porcelain Tile Installed on Level 1
What’s Coming Up
- Continued Flooring, Millwork, and Fixture Installs on Both Levels
- Further construction on Paint Booth #2 & #3
- Installation and Setup of Paint Automation Equipment
Why This Matters
As the physical structure nears completion, we’re not just building a facility—we’re delivering on our promise to improve how we serve our customers, innovate with purpose, and grow with our values intact. This space will better equip us to build and support high-performance emergency vehicles for our customers. Stay tuned for next week’s progress report on the Frazer video page as we cross into the final weeks of this transformational project.