Current Progress
Our team has made great strides in recent weeks, ensuring the project stays on track. Recent highlights include:
- Floors and walls poured for the pits in the expansion area.
- Fire Sprinkler drawings are approved and we received our permits from the city.
- Installing Level 2 aluminum frames for improved structural integrity.
- Slab Pour Back at MEP Underground after we passed our inspections.
What’s Next?
- Setup of fire suppression systems through the whole facility.
- Finalizing exterior site work to improve accessibility.
- Advancing interior construction to shape workspaces.
- Planning for final touches like signage and workspace layout.
Why This Matters
- ✅ Increase production efficiency for faster turnaround times.
- ✅ Enhance our workspace for a better employee experience.
- ✅ Expand capabilities to meet growing customer demand.
We appreciate your support and enthusiasm as we bring this vision to life. Stay tuned for more updates as we get closer to the grand opening!