What’s Been Happening
- Preparations on roof for rooftop AC units
- Installation of drywall at demising wall in Expansion area
- Installation of Overhead Dock Doors at Customer Delivery Area and Warehouse
What’s Coming Up
- Fire Line Excavation and Installation
- Exterior Glass and Glazing at Expansion area
- Exterior Paint at Expansion
Why This Matters
Every curb poured, tile installed, and ceiling framed is a step toward expanding Frazer’s ability to serve our customers even better. This new Sugar Land facility isn’t just a building—it’s a cornerstone of our growth strategy, improving how we deliver high-performance mobile healthcare units and support the Frazer Family for decades to come.
Thank you for following along on this journey. Check back next week for another behind-the-scenes look at our progress.