By: Frazer on June 12, 2025

Robots & Metal Paneling Progress | Building Update – Episode #18

New Production Facility

What’s Been Happening

  • Gantry crane installation begins
  • Installed ceiling tiles, warehouse light fixtures, plumbing fixtures
  • Flooring installation on Level 2

What’s Coming Up

  • Gantry crane installation continues
  • MEP Overhead Fixturing and Trim Out in Warehouse
  • Fire alarm and systems verification

Why This Matters

From expanded floor space to better logistics and climate-controlled work areas, this space is purpose-built to empower our teams, serve our customers faster, and reinforce our commitment to innovation in every custom vehicle we deliver. We’re excited for what’s ahead. Stay tuned for next week’s update as we move into final inspections and system activations.